Choose Language:   Hindi  |  English
 
SEARCH
Home  -  Commercial  -  Overview
 
  Overview
  Generation
  Sales
  Revenue
  Billing and Realization
  Latest Development
  Tariff Petition
  Energy Bills
 
overview back

The 1500 MW (6 x 250 MW) Nathpa Jhakri Hydro Power Station (NJHPS) has been designed to generate 6612 MU of electrical energy in a 90% dependable year with 95% machine availability. Besides, the project has been designed to give valuable peaking power to the Northern Grid.

The first unit of the project has been commissioned on 06.10.2003 with the commissioning of entire station progressively by 18.5.2004. Since start of operations, the station has generated 49632 MU of electrical energy up to 30/09/2011. Out of the total energy generated at the bus-bar, 12% is supplied free of cost to the home state i.e. Himachal Pradesh. From the remaining 88%, 25% energy is supplied to HP at bus-bar rates and balance power has been allocated to different states / UTs of Northern Region by the Ministry of Power, Government of India. The power allocations of the station are as under:

Sl. No. State Allocation (MW) Percentage to the installed capacity
1. Haryana 64 4.27
2. Himachal Pradesh 547 36.47
3. Jammu & Kashmir 105 7.00
4. Punjab 152 10.13
5. Rajasthan 112 7.47
6. Uttar Pradesh 221 14.73
7. Uttarakhand 0 0
8. Chandigarh 08 0.53
9. Delhi 142 9.47
10 Unallocated quota at the disposal of the Central Govt. 149 9.93
  Total 1500 100

The Nathpa Jhakri Hydro Electric Project – NJHEP (1500 MW) being a central sector project of Northern Region, the power being generated is required to be supplied to the beneficiaries of Northern Region which are essentially fourteen in total. Power Purchase Agreements (PPAs) have been signed with all the beneficiaries.

Commercial Performance
The year wise operational and financial break up is as under:

Year Annual Fixed Charge (Cr.)
2004-05 1215.25
2005-06 1429.58
2006-07 1388.60
2007-08 1354.99
2008-09 1312.43
2009-10 1312.43
2010-11 1312.43
2011-12 1312.43

During previous financial year bills of about Rs. 1636.53 crore has been raised against the energy supply up to March, 2011 and Rs. 1715.68 Crore (including UI & interest on UI) has been realized up to 31.03.2011.

During the previous financial year the project has achieved cumulative PAFY of 98.318%.

Besides, SJVN is carrying out customer Satisfaction surveys from time to time and has achieved Customer Satisfaction Index of 98.81 % during FY 2010-11.

The project has so far generated 5876.080 MU during 2011-12 (up to 30/09/2011).

Offtake arrangement: The following table sets out the parties to whom we supply power under PPAs entered into by us with such parties:
Party State Date of commencement of PPA Duration of PPA (years)
PSEB Punjab 24.10.2002 35
HVPNL Haryana 14.01.2003 35
UT,Chandigarh Chandigarh 18.12.2002 35
HPSEB Himachal Pradesh 31.03.2003 40
GOHP(1) Himachal Pradesh 31.10.2005 35
DTL Delhi 27.03.2003 35
PDD(2) Jammu and Kashmir 18.05.2009 05
RRVPNL Rajasthan 28.02.2003 35
UPPCL(2) Uttar Pradesh 18.05.2009 35
UPCL Uttarakhand 22.12.2005 35

Notes:

This PPA does not govern the supply of 12% of annual generation which is required to be made to the state of Himachal Pradesh free-of-charge pursuant to Government policies.

Due to the current imbalance between demand and supply in the Indian power sector, and the competitive rates at which we are able to supply power, we do not currently foresee difficulties with renewing the PPAs when they expire.] Each of our PPAs currently provide that in the event that it expires, the terms of the expired PPA will continue to govern our supply of electricity to such party until the execution of a new PPA or an extension thereto.

   

Copyright © 2007 | Visitor Number:1196932
All rights reserved with SJVN Limited