milestones
Milestones for the year 2011-12

Sr. No.

Description of Milestone

Target date

Status as on 31.12.2011

1

Obtaining Environment Clearance from MoEF

31.07.10

EAC meeting held successfully on 27.12.11. Minutes of meeting awaited.

2

Submission of documents to MoEF for Forest Clearance

30.09.11

 The complete case for forest land diversion was forwarded by DFO to CF, Pauri on 17.12.11. CF, Pauri returned back the case files to DFO on 28.12.11 and asked DM, Chamoli to issue a certificate regarding the status of Civil Forest Land whether it is forest or non forest land with regards to latest Govt. order issued by GoUK.

3

Section 6 notification for Private land acquisition

31.07.10

All 16 case have been submitted by SLAO to Secretary (Energy), GoUk for declaration under Section 6. Being followed up. Section 6 notification for 5 cases has been issued.

4

TEC

30.09.10

DPR submitted to CEA on 29.06.10. CEA Standing Committee meeting held on 14.11.11 in which some observations were raised by the committee. Reply to the observations are being prepared. TEC possible after clearance by Standing Committee.

 

   