Sr. No. |
Description of Milestone |
Target date |
Status up to 30.04.2012 |
|
1 |
Award submission to Govt. of HP for private land acquisition falling under distt. Hamirpur |
31.03.13 |
Draft notifications under Section 6 & 7 for 25 villages of Distt. Hamirpur sent to GoHP on 14.03.12. |
|
2 |
Completion of work of fencing & approach road to existing site office at Jihn. |
15.11.12 |
|
|
3 |
Award for construction of approach road to project |
30.06.12 |
NIT floated on 19.03.12. Technical bid opened on 12.04.12. As per MOU completion date is 30.09.12. |