|
Sr. No. |
Description |
Status as on 30.04.2012 |
|
1 |
MOU |
The MOU was signed with GOHP on 27.10.08. |
|
2 |
a) PEC from state Govt. |
Permission for pre-construction activities was received from State level Environment Impact Authority, GOHP on 03.10.09. |
|
b) PEC from MOEF |
PEC for 66 MW capacity was received from the Ministry of Environment & Forest, GOI on 25.05.10. |
|
3 |
FSR |
Modified FSR (66 MW) submitted to GoHP on 06.04.10 and approved on 05.01.11. |
|
4 |
Exploratory drilling at dam site ( 1140m) |
Completed on 07.06.2010. |
|
5 |
Environment Clearance from MoEF |
Observation/ comments of Expert Appraisal Committee(EAC) meeting held on 11.02.2012 at MoEF, New Delhi being attended. Additional field study completed. |
|
6 |
TEC of DPR |
TEC accorded by GOHP on 25.06.11. |
|
7 |
Exploratory Drift at Dam site. (50 m each on both
abutments.) |
Drifting work: Drift in left and right abutments completed on 25.03.10 & 30.04.10 respetively. Additional drift of 25m on left abutment completed on 19.06.11. |
|
8 |
Identification of land for infrastructure works. |
Public Notice advertised in newspapers on 06.07.11. Five bids were received. Bids opened on 30.08.2011. Tender Committee’s recommendations for technical qualification of bidders under finalization. |
|
9 |
Acquisition of Private land |
The publication process for the issued notifications u/s 6&7 is on for 18 villages in Tehsil Sujanpur,Distt. Hamirpur.
Objection hearing process u/s 5A for 14 villages in Distt. Kangra & one in Distt. Hamirpur completed. |
|
10 |
Diversion of forest land |
Stage-1 approval from MOEF has been obtained on 06.03.2012. Action to attend various points raised in the approval viz. construction of boundary pillars, Payment of NPV & Environment Clearance etc. is being taken. |
|
11 |
Approach road (3.5 KM) to project site. |
NIT floated on 19.03.12. Technical bid opened on 12.04.12 and evaluation of bids in progress. |
|
12 |
License for Explosive Magazine |
Application for grant of license for establishing Explosive Magazine having capacity 3.5 T submitted to Controller of Explosives Nagpur on 27.02.12. |
|
13 |
Work for SIA & SES studies |
SIA & SES studies completed. |
|
14 |
Automatic Weather station. |
Two automatic Weather stations- One at Sujanpur and other near dam site ( in village Jheen) were installed on 10.05.10 and recording of readings in progress. |
|
15 |
Gauge and Discharge site |
Dam site (Near village Amli): Gauge has been established and measurement being done since 17.12.09. |
|
Sujanpur: Gauge & Discharge site has been established at Sujanpur. Measurement of reading started on 31.03.10. |