Monthly Progress Report of Dhaulasidh HEP (66 MW)

Sr. No.

Description

Status as on 30.04.2012

1 MOU The MOU was signed with GOHP on 27.10.08.
a) PEC from state Govt. Permission for pre-construction activities was received from State level Environment Impact Authority, GOHP on 03.10.09.
b) PEC from MOEF PEC for 66 MW capacity was received from the Ministry of Environment & Forest, GOI on 25.05.10.
3 FSR Modified FSR (66 MW) submitted to GoHP on 06.04.10 and approved on 05.01.11.
4 Exploratory drilling at dam site ( 1140m) Completed on 07.06.2010.
5 Environment Clearance from MoEF Observation/ comments of Expert Appraisal Committee(EAC) meeting held on 11.02.2012 at MoEF, New Delhi being attended. Additional field study completed.
6 TEC of DPR TEC accorded by GOHP on 25.06.11.
7 Exploratory Drift at Dam site. (50 m each on both abutments.) Drifting work: Drift in left and right abutments completed on 25.03.10 & 30.04.10 respetively. Additional drift of 25m on left abutment completed on 19.06.11.
8 Identification of land for infrastructure works. Public Notice advertised in newspapers on 06.07.11. Five bids were received. Bids opened on 30.08.2011. Tender Committee’s recommendations for technical qualification of bidders under finalization.
9 Acquisition of Private land The publication process for the issued notifications u/s 6&7 is on for 18 villages in Tehsil Sujanpur,Distt. Hamirpur. Objection hearing process u/s 5A for 14 villages in Distt. Kangra & one in Distt. Hamirpur completed.
10 Diversion of forest land Stage-1 approval from MOEF has been obtained on 06.03.2012. Action to attend various points raised in the approval viz. construction of boundary pillars, Payment of NPV & Environment Clearance etc. is being taken.
11  Approach road (3.5 KM) to project site. NIT floated on 19.03.12. Technical bid opened on 12.04.12 and evaluation of bids in progress.
12  License for Explosive Magazine Application for grant of license for establishing Explosive Magazine having capacity 3.5 T submitted to Controller of Explosives Nagpur on 27.02.12.
13 Work for SIA & SES studies SIA & SES studies completed.
14 Automatic Weather station. Two automatic Weather stations- One at Sujanpur and other near dam site ( in village Jheen) were installed on 10.05.10 and recording of readings in progress.
15  Gauge and Discharge site Dam site (Near village Amli): Gauge has been established and measurement being done since 17.12.09.
Sujanpur: Gauge & Discharge site has been established at Sujanpur. Measurement of reading started on 31.03.10.

 

   
 