Sr. No. |
Description of Milestone |
Target date |
Status upto 31.12.2011 |
|
1 |
TEC of DPR by UK Govt |
30.11.11 |
Due to revision and consequent change in design of Penstock/Pressure shaft, revised DPR has been submitted to GoUK on 29.12.11 for TEC. |
|
2 |
Pubic Hearing |
30.11.11 |
The Draft report submitted to Uttarakhand Environment Protection and Pollution Control Board on 29.10.11 to conduct public hearing. |
|
3 |
Environment Clearance |
31.03.12 |
The draft EIA/EMP Report stands submitted to Uttarakhand Environment Protection & Pollution Control Board (UEPPCB) on 29.10.11.
For NBWL Clearance, the 5 part form has been completed except Part V to be filled by Principal Secretary, GoUK. Accordingly the case submitted by Chief Wild Life Warden to FRDC/Principal Secretary, GoUK. As per FRDC office the case will be first put up to State Board of Wild life and after its clearance the same will be approved by State Govt. The constitution of State Board of Wild Life is under process by GoUK. |