The diversion site is proposed to be located in Purola Tehsil, Distt. Uttar Kashi.
The project proposal was modified and layout was change from right bank to
left bank to optimize the capacity which has been fixed as 60 MW.
PROJECT BENEFITS
Besides the social and economic uplift of the people in its vicinity, the 60
MW Naitwar Mori Hydro Electric Project will generate 265.50 GWH of electrical
energy .PROJECT COST
On completion, the base cost
of project is estimated as Rs. 449.8 crore.
FUNDING PLAN
The project shall be
financed on 70 : 30 debt equity ratio.The equity portion is to be shared
between the Govt. of India ( GOI ) and Govt. of Himachal Pradesh ( GOHP ).
Present Status of Naitwar Mori HE PROJECT
Implementation Agreement for the execution was signed between SJVN Limited and govt. of Uttarakhand on November 21, 2005. Stage-1, site
clearance of MOEF was obtained on February 27, 2006. EIA EMP studies
commenced on July 12, 2006. SJVN has prepared and submitted updated
Pre-Feasibility Report of Naitwar Mori HE Project to CEA on March 25, 2008.
The Detailed Project Report of Naitwar Mori HEP has been submitted to CEA on
July 15, 2008.TEC received on 02.03.2010. EIA/EMP report submitted on 15.03.2011 to Uttarakhand Pollution Control Board. Public Hearing conducted on 03.05.2011. Matter with EAC, MoEF for Final Environmental Clearence.
Completion of Naitwar Mori PROJECT
The 60 MW Naitwar Mori HE Project, is expected in 12th plan period.
|