progress report

MONTHLY PROGRESS OF NAITWAR MORI HEP (60 MW)
 

Sr. No.

Description

Status as on 31.12.2011

1

EIA /EMP Studies Final Environment Clearance was considered by EAC/MOEF during its meeting held on 16.07.11. Additional information/documents asked by MOEF was submitted on 26.09.11. The case has been reconsidered by EAC on 27.12.11 and some more information sought has been submitted to MoEF on 30.12.11.

2

Geological Exploration comprising Surface Mapping, Drilling and Drift works Drilling completed.
Drifting completed.
Widening of area for making space to facilitate Hydrofracture test is in progress.

3

Submission of application for diversion of Forest land & Govt. land Land required for Project Components & Mining: Considering non availability of Civil Soyam Bhoomi for Compensatory Afforestation Plan in Tons Divison, the matter is being pursued with DM for providing 80 hact. land for Compensatory Afforestation. Matter is being regularly taken up with the SDM, Purola for expediting land identification for CA which is now held up due to declaration of elections.

4

Submission of application for acquisition of Private land For land of all the three villages i.e. Bainol, Naitwar & Gainchwan Guan, notices to the land owners have been issued US-IX by DM, Uttarkashi. Matter is being regularly taken up with the DM office regarding deputation of LAO which is now held up due to declaration of elections.

5

Detailed Project Report DPR approved. TEC received on 02.03.2010.
6  Gauge & Discharge data Data is being regularly observed and reported since 20.02.06.

7

Hydro-Meterological observations Recording is being done regularly since 14.02.07.

8

Collection of silt data and its analysis

Regular collection of silt is in progress since 17.07.06.
9 Finalization of Bid Document Tender documents are being revised from EPC basis to item rate basis.
10 Social Impact Assessment SIA Report approved.
11 CAT Plan CAT Plan has been finalized and is under approval by Govt. of Uttarakhand. As per discussion held with Addl. PCCF the CAT Plan will be placed before High Level Committee of Govt. of UK during Jan./Feb. 2012 for approval.

 

   