Milestones for the year 2011-12
 

Sr. No.

Description of Milestone

Target date

Status upto 30.04.2012

1

Submission of final EIA/EMP study report to RGoB

31.07.2012

 

2

Submission of application to RGoB for Environment clearance

31.10.2012

 

 3  Completion of Survey of Approach Roads  31.01.13  

 

   
 