SJVN LIMITED
NATHPA JHAKRI HYDROELECTRIC POWER STATION

Total Power Generated Till Dated 25.07.10 is 39427.237 MU
Year 2010-2011 

DAILY GENERATION  REPORT FOR 25.07.10

GENERATION (MU) 

DAILY

MONTHLY Cuml.

YEARLY Cuml.

 

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

MOU Gross Target

Schedule Target (Ex-Bus)

Gross Achieved

Ex-Bus Achieved

 

 

 

 

 

 

 

 

 

 

  

 

 

35.148

37.023

37.181

36.855

878.720

882.703

889.876

882.434

3112.338

3287.673

3314.448

3286.897

 

 

 

 

 

 

 

 

 

 

Unit No.

Daily (MU)

Running Hours 

Planned Outage

Forced Outage due to break down in M/C

Misc.

Availability 

Remarks

High    PPM/RED

ALERT

Less Avail. of Water

Grid Constraints ETC.

 

Gross

Ex-Bus

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Hr:Min.

Unit - 1 

6.288

6.206

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 2 

6.305

6.247

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 3 

6.014

5.946

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 4 

6.250

6.217

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 5 

6.180

6.121

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

Unit - 6 

6.144

6.118

24:00

0:00:00

0:00:00

0:00

0:00

0:00:00

24:00

 

Total

37.181

36.855

144:00

0:00:00

0:00:00

0:00

0:00

0:00:00

144:00

   

HYDROLOGICAL DATA

Discharge for Generation (Cumecs)
Satluj and Sholding 

Level (Meters)

SILT (PPM)

Inflow for Generation

1301

Max. Dam Level

1495.30

 

Max.

at (Hr.Min)

Min.

at(Hr.Min)

Water Utilized

387

Min. Dam Level

1493.90

Wangtoo

3553

14:00

2583

10:00

Water Spillage

832

Max. TRT Level

1011.5

SFT

N/A

N/A

N/A

N/A

Water utilised for SFT flushing

81

Min. TRT Level

1010.5

Draft Tube

2066

14:00

1343

1:00

 

Coarse Silt Particles

-

Max.

Min.

Dam

NA

NA

Draft Tube

30

9