Power from Dhaulasidh HEP shall be evacuated through the 220 kV network/substation of HPPTCL. The work for construction of the 220 kV transmission line from the switchyard to the HPPTCL network (17 km) was awarded to M/s KEC International Pvt. Ltd. on 14.06.2022. Stage-I Forest Clearance was accorded by MoEF&CC on 29.05.2025, and approval for execution of work on forest land was granted on 06.10.2025. The signing of agreements for the purchase of private land has been completed. Tower foundation and tower erection works are in progress.