Power from the Luhri Stage-1 HEP shall be evacuated from 400/ 220 kV common pooling station proposed to be constructed at Village Ogli by CTU. Work for construction of 220 kV transmission line (34 km) from switchyard to common pooling station (ISTS network) awarded on 06.07.2022. Forest clearance Stage-1 accorded by MOEF&CC on 27.05.2025 and approval for execution of work in Forest land has been received on 25.02.2026. Signing of agreements for purchase of private land in progress. Foundation work for 1st tower has been completed and further work is in progress.